Fugro Seacore (FSCL) has successfully installed three sets
of foundations for Aquamarine Power’s full scale pre-commercial Oyster devices
at the European Marine Energy Centre’s (EMEC) Billia Croo wave test site near the Orkney
Islands near northern Scotland. The devices are wave-powered pumps that push
high-pressure water to drive an onshore hydro-electric turbine.
“A paired foundation was used for the first 800 kW Oyster
800 now successfully installed at EMEC, and two monopiles are successfully in
the seabed ready for two further Oyster devices to be installed to complete the
2.4 MW Oyster array,” explains Bob Jenkins, managing director of FSCL. ”We have
many years’ experience in the renewables sector, and it has been good to
continue our relationship with Aquamarine Power. We wish them every success
with their array.”
“Once again, Fugro completed the work to the highest
standards” says Martin McAdam, CEO of Aquamarine Power. “Their knowledge and
experience of foundation installation is invaluable, particularly in the
testing conditions of Orkney waters. Their work on Oyster 1 led to us choosing
them for the Oyster 800 contract, and we hope that we can continue building our
relationship with Fugro Seacore in the future.”
The $4.75 million contract for the foundations follows on
from FSCL’s successful involvement in the installation and commissioning of the
single full-scale 315 kW Oyster 1 at EMEC in 2009. At the time of signing the
contract Martin McAdam remarked that: "This deal shows that a thriving
marine energy sector has the potential to offered skilled jobs and economic
opportunity the length of the UK.”
The installation of the foundations this year saw FSCL use
in-house owned-and-operated equipment, including the jackup barge ‘Excalibur’
with the T40 reverse-circulation drill rig and grouting equipment. To achieve
the required positional tolerances for the paired foundation, FSCL designed,
built and commissioned a bespoke twin pile gate.
“Pile gates were used during drilling of the rock sockets
for each pile, and to support each pile during installation,” explains Bob
Jenkins. “These bespoke gates, which measure 112 feet long, 12.5 feet wide and 11.5
feet high, were able to move both vertically and horizontally using hydraulic
pinning systems, enabling accurate positioning of the piles into position. The
pile gates ensured the correct position of the piles, and held them securely in
place after they had been grouted and during the grout-curing period.”
In total, nearly 1,650 cubic feet of sandstone was drilled
and excavated, four 95-tonne large-diameter piles were installed, and 495 cubic
feet of grout was mixed and pumped over the 34-day operational period.
Harnessing Wave Power
Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!