Hammer and Steel Foundation Rigs to Help Build Brooklyn High-Rise
ECD NY Chooses Hammer and Steel Equipment for 50-Story Project
The building was designed by Dattner Architects, construction is being managed by New Line Construction, and ECD NY has been subcontracted for the building’s foundation.
Two Mobilram rigs will be used to install over 450 micropiles, which are 16 inches in diameter and being drilled to a depth of 120 feet to bedrock. The Mobilrams have been equipped with VDW double-head drilling systems and 20-inch micropile clamp-and-breaker systems specifically for this job.